San Pablo Avenue

Streetscape Improvements

San Pablo Avenue Phase 2

The Vision

The City of Palm Desert will continue transforming San Pablo Avenue from Fred Waring Drive to Magnesia Falls Drive. San Pablo Avenue - Phase 2 improvements include two new roundabouts, one at Magnesia Falls Drive and one at the entrance to the College of the Desert.

Additional project features include enhanced pedestrian walkways, landscape/hardscape improvements, streetlighting, on-street parking, pedestrian crosswalks, improved bikeway facilities, complete removal and replacement of existing pavement, and traffic signal improvements.

These improvements will complement the recently completed Phase 1, south of Fred Waring Drive to Highway 111, and connect San Pablo to CV Link, the 40+ mile pathway that will provide a safe and active alternative transportation route across the Coachella Valley.

Project Fact Sheet

Envisioned Changes

Roundabout at Magnesia Falls Drive
Roundabout at the entrance of College of the Desert
Enhanced Pedestrian Walkways
On-Street Bikeway
On-Street Parking
Decorative Hardscape
Landscape and Shade Trees
Traffic Signals
New San Pablo Avenue Roadway Pavement

Project Limits

On San Pablo Avenue from Fred Waring Drive to Magnesia Falls Drive

Project Schedule

Start | October 26, 2020
Completion | June 2021*
*Construction schedules are subject to change

Stage 1

October 26, 2020 - January 2021
Partial Closure: San Pablo Avenue from Civic Center Drive Way to Magnesia Falls Drive

Stage 2

January 2021 - June 2021
Full Closure: San Pablo Avenue from Fred Waring to Magnesia Fall Drive

Work Hours

October 1 - April 30*
M-F (7am - 5:30pm) Sat. (8am - 5pm)
Sundays and Holidays – No work Allowed
*Nighttime hours are subject to City approval